Downtown Algonquin Construction Update (from Public Works):

Here's what crews accomplished this week:

Continued installing the sanitary sewer on La Fox River Drive near the lift station.

Poured the slab on grade* for the control building at the lift station.

Finished pouring concrete for the second stage of N. Harrison Street - all pavement and various sidewalk patching is complete.

*A type of foundation

Here's what crews will be working on next week:

Continuing sanitary sewer installation on La Fox River Drive and making the final connection to the existing sanitary sewer on Center Street.

Installing the electrical service for the control building.

Completing all outstanding concrete patchwork on Harrison Street.

Starting landscape restoration on Harrison and Washington streets and remaining parts of La Fox River Drive.

Detours and Closures

N. Harrison Street is open between Algonquin Road and Front Street but is only accessible from Front Street (No access from Algonquin Road).

N. Harrison Street between Front and Edward Streets will remain closed through the middle of next week.

La Fox River Drive between RT 31 and Center Street as well as Center Street north of La Fox River Drive remain closed.

Stage3 Detour map Dec 12.png