Old Town Construction Update (from Public Works): This week, crews completed installation of the odor control unit at the lift station. Crews will now begin testing the startup of the generator control building and lift station. Once testing is complete, these facilities will be put into service.
Over the next few weeks, the contractor will replace the remaining curb and sidewalk around La Fox River Drive and Center Street. The contractor will also be placing the concrete patch along La Fox River Drive and at the intersection with Route 31. When this work occurs, the contractor will need to close La Fox River Drive between Route 31 and Center Street. Residents should utilize the surrounding side streets to access Route 31. Any resident living in the impacted area will be notified of access restrictions prior to the closure.
The contractor will also begin restoration work in the next several weeks. This works will focus on the remaining turf areas that have been disturbed during construction as well as the field at the intersection of Algonquin Road and Harrison Street.
The contractor also plans to complete the remaining paving work once the asphalt plants reopen for the year, traditionally this occurs at the end of April.
http://oldtownalgonquin.org/stage-3-south-harrison-street...