Prairie Path Construction Update (from Public Works):

Last week, crews placed the concrete for the bridge abutments that will hold the new pedestrian bridge.

This week, the team will deliver and install the pedestrian bridge, which will bring a new look, feel and support for bicyclists, pedestrians and all trail users. On Tuesday, crews plan to place the concrete for the wing walls. The team will then haul the pre-fabricated bridge structure up La Fox River Drive approaching the trail from the south side. A large crane will be in place to lift bridge structure into place on Wednesday, July 1. The bridge abutments will hold the new bridge higher above ground to allow vehicles to safely pass under it.

Please note: There are free, public parking lots near the trail (marked on the detour map below). Please park in these lots and not in the construction zone. Also, as an important reminder, during COVID-19 we ask that trail users not stop and congregate on the trail.

Thank you for your patience and cooperation as we construct this project!

Construction Detour:

The temporary ramp will route users to La Fox River Drive onto local streets where they can safely reconnect to the Prairie Trail through Towne Park. Please utilize the free, public parking lots indicated on the map. For safety purposes, we kindly ask that you walk your bicycle while in the construction zone.

http://oldtownalgonquin.org/index.html

Old Town Algonquin

Downtown Algonquin Construction Update (from Public Works):

Last week, crews completed pavement restoration at the intersection of Algonquin Road and Main Street and have reopened the intersection.

Crews will complete the remaining water main work under Algonquin Road at the intersections of Main and Harrison streets once IDOT shifts traffic from the north to the south side of Algonquin Road for their bridge construction project.

The team also continued installing the sanitary sewer along the 400 block of La Fox River Drive.

Next week, crews will continue installing the sewer along La Fox River Drive. Residents in the immediate construction area should note that access to their driveways may be limited during the day. A member of the construction team will notify residents of driveway access restrictions in advance, either in person or with a construction notice door hanger. Additionally, residents along the east side of La Fox River Drive should know that as the sanitary sewer installation progresses past their home, residents could see a disruption of water services. If your water services will be impacted, a member of the construction team will provide 48-hour advanced notice of the disruption, either in person or with a construction notice door hanger.

http://oldtownalgonquin.org/stage-3-south-harrison-street.h…

Pedestrians and bicyclists should use the east sidewalk on La Fox River Drive to access the Prairie Trail.

Downtown Algonquin Construction Update (from Public Works)

Last week, crews finished the installation of the new water main casing and poured the concrete base for the roadway at the south half of the intersection of Algonquin Road and Main Street. The construction team also completed installing the new sanitary sewer along La Fox River Drive through the 600 block. Crews anticipate completing the sanitary sewer work past the Prairie Trail today. In order to provide safe access during this work, flaggers will be on-site to direct pedestrians and bicyclists around construction.

On Monday, June 22, the contractor will place the final asphalt patch for the work at the Algonquin Road and Main Street intersection. The team plans on reopening the road by the end of the day on Tuesday, June 23. We appreciate everyone's patience during this process as we coordinated our schedule with the IDOT bridge construction project.

Next week, crews will continue installing the sewer along the 400 block of La Fox River Drive; flaggers will be present in this area to safely direct pedestrian and bicycle traffic. Residents in the immediate construction area should note that access to their driveways may be limited during the day. A member of the construction team will notify residents of driveway access restrictions in advance, either in person or with a construction notice door hanger. Additionally, residents along the east side of La Fox River Drive should know that as the sanitary sewer installation progresses past their home, residents could see a disruption of water services. If your water services will be impacted, a member of the construction team will provide 48-hour advanced notice of the disruption, either in person or with a construction notice door hanger.

Water main installation and concrete base placement

On Friday, did you notice a giant crane in town? Crews took advantage of the intersection closure and installed the remaining decorative elements on the bridge. New flower boxes and fascia was installed along the bridge. Flowers will be planted next week to complete this project.

http://oldtownalgonquin.org/stage-3-south-harrison-street.h…

Detour Information:

The Village will maintain two-way, local traffic on Main Street from Washington Street to Historic Village Hall/Rt. 62 (where the road closure will be located) and between Main and Edwards streets. The private alley next to The Black Bear Bistro will be available as a “one-way west” exit off Harrison Street to access Main Street. East bound traffic can use the parking lot behind Historic Village Hall to turn around.

The detour along La Fox River Drive remains in place. The intersection of Algonquin Road and Main Street will remain closed for construction through June 23.

This project is expected to take approximately 10 months to complete. We appreciate everyone’s patience and understanding as we invest in this important infrastructure project to improve the community.

Prairie Trail Construction Update (from Public Works)

Last week, crews were able to install the new pergola! This elegant structure matches the features in the downtown area and will create a place for residents and trail users to pause and relax.

This week, progress will resume work on the pedestrian bridge. With warmer temperatures and drier conditions, the construction crew will be able to place the concrete for the bridge abutments. Once the abutments (supports walls) are complete, the new prefabricated bridge, which was constructed offsite, can be delivered and installed.

Please note: There are free, public parking lots near the trail (marked on the detour map below). Please park in these lots and not in the construction zone. Also, as an important reminder, during COVID-19 we ask that trail users not stop and congregate on the trail.

Thank you for your patience and cooperation as we construct this project!

http://oldtownalgonquin.org/index.html

Water Main Work/Road Closure June 15-24 (from Public Works)

From June 15-24, Main Street at IL-62 will be closed for water main work. We will maintain two-way, local traffic on Main Street from Washington Street to Historic Village Hall/IL-62 (where the road closure will be located). The private alley next to The Black Bear Bistro will be available as a “one-way west” exit off Harrison Street to access Main Street. East bound traffic can use the parking lot behind Historic Village Hall to turn around.

Take advantage of reduced traffic to walk, dine outdoors and shop more freely at our amazing #Algonquin businesses along Main Street! #construction #ShopLocal

Learn more at http://ow.ly/MPbi50A6s0A

Main Stree June 12.jpg

Remote Village Meetings - Tuesday, June 16, 2020

There are 3 remote Village meetings scheduled for Tuesday, June 16 starting at 7:25 p.m., including: Liquor Commission Special Meeting, Village Board Meeting, and Committee of the Whole Meeting. The Liquor Commission will discuss the application for B-2 Liquor License for 7-Eleven at 10 S. Randall Rd.The Village Board Meeting agenda includes: approval of prior meeting minutes; ordinances & resolutions on liquor licensing, surplus items, parking lot easement, replacement of pressure reducing valves and sewer lining project; payment of bills; Financial Resilience Plan update, and continuation of proclamation of local disaster emergency through 7/21/2020. The Committee of the Whole agenda items include: Final Plat, final PUD & special use permit for land near SE corner of IL Rt. 62 & Compton Drive; pressure reducing valve professional oversight services; and Executive Session (land acquisition). Please refer to links for public comment/participation or to listen to the meeting, and meeting packets.

https://www.algonquin.org/eg…/documents/1591974941_70461.pdf

https://www.algonquin.org/eg…/documents/1591974638_78043.pdf

https://www.algonquin.org/eg…/documents/1591974798_09469.pdf

Remote Village Meetings Tuesday, June 9, 2020

The remote Village of Algonquin meetings scheduled for Tuesday, June 9th include: Public Hearing (Rebuild IL Fast-Track Public Infrastructure Grant);Committee of the Whole; and Special Village Board Meeting(Resolution regarding Rebuild IL Grant). The Public Hearing will begin at 7:25 p.m. Please refer to links for public comment instructions; meeting phone in/zoom instructions, agendas, and meeting packets.
https://www.algonquin.org/eg…/documents/1591379298_27098.pdf
https://www.dropbox.com/…/sv4h3b…/AACnqG-MER9bRZR9BZ-w4x1ra…
https://www.algonquin.org/eg…/documents/1591381375_86489.pdf
https://www.algonquin.org/eg…/documents/1591380538_25779.pdf

Construction Update 5/30 (from Public Works)

Sanitary manhole installation/Sewer jack and bore/Water main installation

This week, crews finished installing the water main on the south side of Algonquin Road at Harrison Street. The contractor plans to put the new water main in service by the end of next week, after completing the connection to the existing water main. Crews also finished installing the 48” steel casing under Algonquin Road at the intersection of Harrison Street. The construction team has installed the 30” sanitary sewer within the casing and the associated manholes on both sides of the casing.

Next week, crews will begin work on the pavement restoration for the water main and sanitary sewer at the intersection of Algonquin Road and Harrison Street, which they expect to finish the second week of June. Once the crews complete the pavement restoration, the intersection of Algonquin Road and Harrison Street will be reopened.

Here's what to expect in the coming weeks:

The contractor anticipates that crews will resume installing the sanitary sewer along La Fox River Drive the second week of June. Around the third week of June, crews will install the south half of the casing across Algonquin Road at the intersection of Main Street. This intersection will be closed while crews complete this work.

Detour:

Due to the construction coordination at the bridge, access onto Algonquin Road from North and South Harrison streets will not be permitted. Please follow the detour route on Main Street to bypass this work zone.

Traffic will be routed along Route 31 to Main Street and then back to Washington Street and La Fox River Drive.

We ask that drivers, pedestrians and bicyclists use caution due to the level of construction equipment along La Fox River Drive.

This project is expected to take 10 months to complete. We appreciate everyone’s patience and understanding as we invest in this important infrastructure project to improve the community.

http://oldtownalgonquin.org/stage-3-south-harrison-street.h…

Remote Village Board Meeting - Tuesday, June 2

The Village Board meeting for Tuesday, June 2nd will be held remotely starting at 7:30 p.m. Please refer to meeting packet link to submit public comments; give comments during the meeting public comment portion; and agenda details. Agenda items include: approve prior meeting minutes; pass ordinances on amending Ch. 33 Liquor Control & Liquor Licensing; execution of a Declaration of Covenants with the Village of Cary; Intergovernmental Agreement between Cary & Algonquin for jurisdictional transfer of land north of Klasen Road; disconnect certain property lying north of Klasen Road; adopt resolutions with Christopher Burke Eng. for Rt. 62 bridge deck overlay, Sleepy Hollow Project oversight, GASB entry services and engineering consulting; and approve bills for payment.

https://www.algonquin.org/eg…/documents/1590765935_11547.pdf

Remote Village Board Meeting & COW Meeting - Tuesday, May 19

There are two remote meetings on Tuesday, May 19 starting at 7:30 p.m. Note: Redevelopment of Terrace Lakes Golf Course - Commercial lot has been removed (p. 511 of meeting packet). Please refer to link for Village Board meeting agenda, public comment/participation instructions, and agenda item details. https://www.algonquin.org/eg…/documents/1589638773_33054.pdf

The Committee of the Whole (COW) meeting will immediately follow the Village Board meeting. Agenda items include amending Ch. 33 Liquor Control & Liquor Licensing; agreement for construction oversight with Christopher Burke Eng. for Rte. 62 bridge deck overlay; Sleepy Hollow Project; and GASBY entry; and extending engineering consulting services with Christopher Burke Eng. Please refer to link for meeting packet.

https://www.algonquin.org/egov/documents/1589638956_9134.pdf

Remote Committee of the Whole Meeting - Tuesday, May 12

The Committee of the Whole meeting will be held remotely on Tuesday, May 12 at 7:30 p.m. The following items are on the agenda: revised Trails of Wood Creek development plan; restaurants & outdoor seating on public property; Agreement with Trotter & Associates for phosphorus discharge & optimization plan; surplus vehicles; Agreement with McHenry County Conservation to connect Maker's Park Trail from Armstrong St. to Prairie Trail and Agreement with DK Contractors for construction of Maker's Park bike path.Please refer to attached links for the meeting packet, public comment directions and zone meeting information.

https://www.algonquin.org/eg…/documents/1588975429_52473.pdf

https://www.algonquin.org/eg…/documents/1588975448_46405.pdf (Part 1)

https://www.algonquin.org/egov/documents/1588975478_7636.pdf Part 2 (revised Trails of Wood Creek Dev. Plan)

Stage 3 Water & Sewer Improvements (from Public Works)

Last week, crews installed almost all of the de-watering wells and will install the remaining wells as work progresses. Crews also began installing the 30-inch sanitary sewer north along La Fox River Drive from Center Street. To date, they have installed approximately 120 feet of sewer.

On May 5, the IDOT Algonquin Road (Route 62) bridge project will begin. At that time, the Stage 3 contractor will halt installation of the 30-foot sanitary sewer along La Fox River Drive so they can focus on the work being done in conjunction with the IDOT project. During the first stage of the IDOT project, the Stage 3 crew will install a 48-inch casing pipe for the sanitary sewer through the intersection of Algonquin Road and Harrison Street (this pipe will be bored or drilled under the roadway). Also during the first stage, crews will install water main within the south half of the intersection of Algonquin Road and Harrison Street, as well as along the south side of Algonquin Road from the intersection to the bridge over the Fox River. Additionally, crews will install water main across the south half of the intersection of Algonquin Road and Main Street. During the second stage of the IDOT project, the remaining water main will be installed across both the Harrison Street and Main Street Algonquin Road intersections.

New Detour:

An additional detour will be starting Monday! Due to the construction coordination at the bridge, access onto Algonquin Road from North and South Harrison streets will not be permitted. Please follow the detour route on Main Street to bypass this work zone.

Traffic will be routed along Route 31 to Main Street and then back to Washington Street and La Fox River Drive.

We ask that drivers, pedestrians and bicyclists use caution due to the level of construction equipment along La Fox River Drive.

Stage 3 logo vF _002_.png